Peterson Hall Construction Log

This page is updated weekly.

Week Ending August 22nd

Carpeting finished in classrooms. Data projectors installed in all four rooms. Equipment racks/credenzas arrive and audio-visual wiring to them partly done in two Plaza level classrooms. Work on frame areas around Plaza level entrance doors completed. New phone and data wiring 50% complete. New restroom substantially complete (one fixture item not available; change made).

More Photos from August 22nd

Plaza Level

PH110 and 111

Other Areas

First First

Week Ending August 15th

Painting done in Plaza level classrooms, ceiling grid, lighting fixtures, and entrance doors installed. Scaffolding removed from PH110. Floor covering finished in PH112, sinks and fixtures installed. Duct work completed in staff lounge, ceiling replaced, duct enclosures painted. Ceiling installed in 111; waiting for light fixtures. Stairs carpeted in 110; centercarpeting installed in 110 and 111. Work begins on audiovisual system wiring and network and telephone wiring.

More Photos from August 15th

Plaza Level

PH110 and 111

Other Areas

First First

Week Ending August 8th

Painting begins: west wall of restroom (ph112), west wall of ph111 and new south wall in ph110. Most ductwork in main project area finished. Ceiling grid installed in ph111. Walls in Plaza A and B taped, sanded, ready for painting. Start on flooring in ph112. Electrical work continues. Replace some glass panels along south side of Plaza level with tempered glass.

More Photos from August 8th

Plaza Level

PH110 and 111

Other Areas

First First

Week Ending August 1st

Install insulation in wall between Plaza A and B and along north wall dividing A and B from 110. Re-finish false ceiling over front of 110 where support beams for old partition tracks were removed. Continue installation of electrical lines and HVAC duct and plumbing. Finish up drywall.

More Photos from August 1st

Plaza Level

PH110 and 111

Other Areas

First First

Weeking Ending July 25

Electrical and audiovisual conduit in all spaces. Drywall along west wall of Plaza A and east side of wall between Plaza A and Plaza B. Drywall(double layer) up on large wall along south of PH110 and insulation and drywall in new rest room. Remove portion of heavy support beams for old partition wall tracks along the front of PH110. Cut in threshold areas for Plaza classroom street-side doors. Continue installation of HVAC ductwork and fluid pipes in staff lounge and extending through to Plaza level classrooms. Problem to resolve regarding electrical access panels along north end of Plaza level rooms.

More Photos from July 25th

Plaza Level

PH 110 and 111

Other Areas

First First

Weeking Ending July 18

Begin framing walls of new restroom and Plaza level classrooms. Remove existing light fixtures above Plaza Level. Remove original partition wall track above Plaza B (front of old PH111). Set up scaffolding in PH110 for wall construction between 110 and the Plaza level, 111, and crawl spaces. Begin north side drywall along demising wall between 110 and rest of project. Begin installation of conduit and receptacles in new spaces.

More Photos from July 18

Photos

PH 110 and 111

Other Areas

First First

Week ending July 11

Drop in conduit for new floor. Pour concrete for new plaza level floor. Cut HVAC duct openings through floor in staff lounge. Removal of the rest of the drop ceiling from PH111. Fireproofing on new structure. Set in new steps along the south side of PH110.

More photos from July 11

More Photos

Rooms 110 and 111

Other Areas

First First

Week ending July 3

Finish up fastening deck plates. Install rebar over steel deck for new floor. Concrete pour for Thursday postponed: Supplier over-subscribed. Re-inspect curb work on roof.

First First

More photos from July 3

More Photos

Week ending June 27

Set new floor support beams onto support wall. Lay out and secure metal decking. New heating and cooling units delivered and located on roof.

First First

More photos from June 27th

Support Structure
HVAC Unit

Week ending June 20

Support walls built for the floor of the two new classrooms. Sewer trench filled in in restroom. Preparation work on the roof of Peterson for installation of HVAC units. Some HVAC ductwork delivered.

First First

More photos from June 20th.

New Walls
Other Areas

Week ending June 13

Trenching for support wall footings completed; concrete poured and cured. Additional ceiling removal in 111. Begin cutting for roof openings for HVAC ductwork. Installation of plastic drain pipe to sewer from new restroom.

First First

More photos from June 13th.

Cement Pour
Other Areas

Week ending June 6

Additional earth removal required for footings; completed. Begin aggregate fill and compacting for footings. Removal of ceiling west end of 111 to expose concrete prior to cutting for heating/cooling ductwork. Make decision on room lighting fixture changes and egress lighting. Renovation begins on existing men's restroom for ADA compliance. Start on trenching for pipe for new women's restroom (also ADA compliant).

First First

More photos from June 6

Week ending May 30

Earth removal for new footings substantially completed. Testing soil moisture required for area of new footings. Conduit beneath old benches cut down below floor level. Discuss options for egress lighting. Rebar for concrete pour delivered. Some structural steel delivered. Cinder block delivered. Audiovisual equipment ordered.

First second

More photos from May 30

Week ending May 23

Decisions on new ADA-compliant women's restroom. Determine sewer pipe location. Earth removal for new footings continued. All concrete cuttings and earth removed carried out of the building by wheelbarrow.

No photos for this week.

Week ending May 16

Began removal of the overhead tracks for the movable room divider. Discovery of older tracks for a previous divider. Mount locations for new floor support beams cut into east wall. Survey of roof concrete supports for heating/cooling ductwork path. Clear area in staff lounge where heating/cooling ductwork will route between roof and new rooms.

First second

More photos from May 16

Week ending May 9

Concrete cutting began in 111. Most existing north and south steps to be removed and tops of two risers to be cut away. Removal of wall sections of the movable divider between PH110 and 111. Removal of brick facade from west wall of 111. Old counters in the front of both PH110 and PH111 removed. Asbestos abatement above ceiling in staff lounge.

First second

More photos from May 9

Week ending May 2nd

Construction operations began with setup of contractor's office and light demolition in PH111. All seats were removed from PH111 and south hand rail removed. Seats from PH111 in good condition identified to be used to replace worn or missing seats in PH110. Removal of carpeting. Linfield staff removed contents from storage in PH112 to temporary storage pod. Asbestos abatement on the tile in 112.

First second

More photos from May 2nd